EXPERT PROFILE
Expert number: 300777
Civil/Highway Engineer
Employee of firm or organisation
Uganda Contact details hiddenTo see contact details you need to use an expert credit.To use a credit, or if you have none buy some, click the link below. View contact details Professional Information
General DescriptionCountriesPreferred countries: Abu Dhabi, Bahrain, Bhutan, Dubai, Egypt, Arab Rep, Ethiopia, Falkland Islands, Fiji, Fujairah, Gambia, The, Gibraltar, India, Libya, Malaysia, Maldives, Mali, Mauritius, Namibia, Nepal, Netherlands, New Zealand, Oman, Russian Fed, Saudi Arabia, South Africa, Sri Lanka, UAE, Uganda, UKExperience in: Botswana, India, Iraq, Mali, Uganda ServicesTeam Leader shall be responsible for reviewing the entire Project preparation and implementation activities of the Concessionaire. He shall check all the Designs being prepared by the Concessionaire, ensure execution of works on site as per specification and standards, and continuously interact with the NHAI and the Concessionaire. He shall undertake Project site visits and shall guide, supervise, coordinate and monitor the work of other experts in his team as well as those of the Concessionaire. Team leader shall close min. 5-10 per cent of Concessionaire’s request for Inspection (RFI), as per the provisions of Concession AgreementSpecialisationsBUILDINGS - Educational. Housing. Industrial. Institutional. Office/commercialENVIRONMENT - Sewage disposal INFRASTRUCTURE - Airports/air transport. Bridges/viaducts. Harbour/sea/river works. Highways/road transport. Industrial estates. Pipelines. Residential estates EDUCATION - Higher education Employment HistoryShapoorji and Pallanji in India
for Shapoorji and Pallanji in
India 2000 - 2000 1. Responsible for supervising of site works 2. Managing resources for planning of works to be executed 3. Coordinating site staff, client etc 4. Establishing Quality Assurance System, setting up site laboratories and ensuring tests of all materials and components of works at various stages of construction 5. Improvement of quality checks and assurance of the quality to the satisfaction of the client. Audco International, Mali in Mali
for Audco International, Mali in
Mali 2000 - 2000 • Material & Subsoil Investigations • Selection of borrow pits /quarries for construction materials • Checking of Designs & Drawings • Preparation of standards & specifications for construction • Finalise Quality Control Plan & Environmental Protection measures • Responsible for establishing Quality Assurance system by setting up site laboratories and ensuring tests of all materials and components of works at various stages of construction. • Approving job mix formulas for sub base, base course, studying materials report and test results • Inspection of plants & Equipment • Checking of fitness of the equipment and calibration time to time, checking of quality at all levels during the period of construction to the satisfaction of client. Dr,Ing Walter International in Iraq
for Dr,Ing Walter International in
Iraq 2000 - 2000 During Design stage, he was responsible for conducting field surveys, Material & Geotech investigations, Preparation of Material specifications & standards, Material Sources identification 1. Involved in supervision of Detailed Designs & Drawings for 4 laning of the Road 2. Establishing Quality Assurance system by setting up site laboratories and ensuring tests of all materials and components of works at various stages of construction 3. Devising control test procedures, guiding mix designs, selection of borrow pits for soil investigations &quarries for raw materials 4. Approving job mix formulas for sub base, base-course, design of mix asphalt and cement concrete, checking laying procedures 5. Studying materials report and test results 6. Inspection of function of plants equipment 7. Checking of concrete mix design, testing of strength of concrete, checking of fitness of the equipment and calibration time to time and checking of quality at all levels during the period of construction to the satisfaction of client 8. Preparation of maintenance manual, and inspection of pavement during Defect liability period. Rites Ltd in India
for Rites Ltd in
India 2000 - 2000 • Organising field studies, sub soil & hydrological investigations for improvement of Road geometry and alignment. • Preparation of GAD, Geometric Designs, L & C sections • Co-ordination for Environmental & social studies • Preparation of Detailed Engineering Designs & Drawings and Detailed Project Report • Timely completion of works by taking quick decisions • Approving contractor's work programme, construction management plan • Preparation of quality assurance plan • Setting up of field laboratory • Inspection of Performance of work as per drawings, specifications and contract stipulations • Carry out Quality and quantity checks, issue site instructions, • Preparation of progress report • Certification of bills, verification of contractor's statement • Completion of As-Built drawings • Training to technical staff of the Road Dept. In Preparation of Tender Documents, Evaluation of Tenders. • Review of design & drawings prepared during DPR and modification as per site condition or desired by Client with application of Soft desk, AutoCAD, MS Road. • Construction administration and Supervision of works carried out by contractor under FIDIC condition of contract. • Checking tests Results on completed items of pavement. • Identifying borrow areas locally available to suit with the technical specifications. • Review of safety measures proposed for traffic and ensures implementation. Unitech Ltd in India
for Unitech Ltd in
India 2000 - 2000 Responsible as Sr. Project Manager / Project Manager, for : • Evaluation of Tenders, Awarding works to contractors, Selection of Consultants and advisers, • Study and reviewing of available data, reports and drawings • Reviewing of work methodology and quality control plan • Inspection of laboratories, plant and equipment such as Asphalt mixing plant, wet mix macadam, anti corrosion treatment plant • Suggesting modifications in design of pavement • Review of mix designs for high strength concrete/Asphalt concrete. • Inspection and supervision of construction on preparation of variation orders, conducting site meetings and progress reports. • Inspection of performance of work as per drawings, specifications and contract stipulations, quality and quantity checks, issue site instructions • Preparation of progress report, examine& certification of bills, verification of Contractor’s Completion statement, completion of As-Built drawings. Govt of Botswana in Botswana
for Govt of Botswana in
Botswana 2000 - 2000 • Organising field studies, sub soil & hydrological investigations for improvement of Road geometry and alignment. • Preparation of GAD, Geometric Designs, L & C sections • Co-ordination for Environmental & social studies • Preparation of Detailed Engineering Designs & Drawings and Detailed Project Report • Timely completion of works by taking quick decisions • Approving contractor's work programme, construction management plan • Preparation of quality assurance plan • Setting up of field laboratory • Inspection of Performance of work as per drawings, specifications and contract stipulations • Carry out Quality and quantity checks, issue site instructions, • Preparation of progress report • Certification of bills, verification of contractor's statement • Completion of As-Built drawings • Training to technical staff of the Road Dept. In Preparation of Tender Documents, Evaluation of Tenders. • Review of design & drawings prepared during DPR and modification as per site condition or desired by Client with application of Soft desk, AutoCAD, MS Road. • Construction administration and Supervision of works carried out by contractor under FIDIC condition of contract. • Checking tests Results on completed items of pavement. • Identifying borrow areas locally available to suit with the technical specifications. • Review of safety measures proposed for traffic and ensures implementation. Rites Ltd in India
for Rites Ltd in
India 2000 - 2000 As Acting Resident Engineer Responsible for: Project planning & execution, Environmental Impact Assessment, Quality Assurance norms. • Review of sub-soil & Geotechnical Investigations. • Detailed design reviews, checking design parameter, finalization of alignment survey & FRLs. • Checking of Design of road drainage system, intersections, junctions, service roads. • Finalize Methodologies for all road construction activities, Traffic & Safety Management Plan, road signage’s, road marking, signalized junction, Truck parking areas and bus-lay byes etc. • Suggesting modification of construction programme, construction methodology. • Review & Approval of Environmental Management Plan, Quality Assurance programme. • Ensure timely Issuance of approve working drawings & construction Drawings. • Approval of Works, Quantity Survey, and Reviewing Progress of woks • Quality control of Works, Ensure Implement of Quality Assurance Programme by Contractor. • Construction Supervision of works • Checking of As Built Drawings, Contractors Final Statement of Account Claims. • Coordination with Client and Contractor and local Government Agencies. • Project is scheduled for completion before Six Months against targeted Schedule enabling Contractor to claim Bonus of 5% of Contract Value. • Giving Approval on budget allocation of Road Sector activities. • Setting up of Technical norms. • Environmental Mitigation measures. Implementation of Condition of Contracts. • Monitoring of Progress and Preparation of Monthly Progress Reports and suggesting remedial measures. • Review and evaluation of variation claims of contractors • Project Implementation Unit Buildings (Office& Residential) RAFU,Governament of Uganda in Uganda
for RAFU,Governament of Uganda in
Uganda 2000 - 2000 As Team Leader, responsible for a. Detailed Project Report for 53 km road of strengthening existing road. b. Leading Team of Engineers for Geometric and Pavement Design. Construction Supervision c. Monitoring contractor’s work Programme, Progress of works, issuing in trim payment certificate. d. Co-ordinating with client, advising Client on Contractor’s claims, Preparing variation Orders, Issuing Working Drawings. As Material Engineer, Responsible for establishment of Laboratories and review of quarry sites, supervision of works, Quality control and evolving Quality Assurance system, approving source of materials, inspecting the performance of work vis-à-vis Workmanship, specifications and quality check tests, reviewing and approving manufacturing test certificates, studying material reports and test results, approving job mix formula / mix design, maintaining records of tests. Howe India Pvt Ltd in India
for Howe India Pvt Ltd in
India 2000 - 2000 • Responsible for Contract Management. • Estimations of Works. • Deployment of plant and equipment, measurement of completed works. • Maintenance of construction records, issuing of site instructions and progress monitoring. Director, Central Building Rsearch Institu in India
for Director, Central Building Rsearch Institu in
India 2000 - 2000 Responsible for planning for scientific research projects for buildings, designing foundations (Under Reamed Piles and raft foundation). Critical analysis of Research projects conducted in India in various research Labs on Geotechnical subjects. Strengthening of existing 2-lane Carriage way
for Road Formation Unit,Govt.of Uganda in
Uganda 2000 - 2000 Strengtening of Existing 2-lane 54km Road With 175 mm Cement Stabilized Base,Double sealing and Upgrading Driage System. Widening to 4-lanes and strengthening of 2-lane carriageway of NH-5 from Km 2.8 to km 98.0
for NHAI in
India 2000 - 2000 Construction supervision of Widening to 4-Lanes and Strengthening of 2-lane Carriageway of NH-5 from Km 2.8 to km 98.0 (Visakhapatnam-Srikakulam) in the state of Andhra Pradesh (Package AP-5) including major Bridges & Flyover. Client : NHAI; Project Cost : Rs. 4820 M Project Length : 96 Kms.; Contract Condition : FIDIC Period : Aug 2001 to Aug 2004 Duties Rendered : Widening to 4-lanes and strengthening of 2-lane carriageway of NH-5 from Km 2.8 to km 98.0
for NHAI in
India 2000 - 2000 Construction supervision of Widening to 4-Lanes and Strengthening of 2-lane Carriageway of NH-5 from Km 2.8 to km 98.0 (Visakhapatnam-Srikakulam) in the state of Andhra Pradesh (Package AP-5) including major Bridges & Flyover. Client : NHAI; Project Cost : Rs. 4820 M Project Length : 96 Kms.; Contract Condition : FIDIC Period : Aug 2001 to Aug 2004 Duties Rendered : Widening to 4-lanes and strengthening of 2-lane carriageway
for Raods Department,Govt.of Botswana in
Botswana 2000 - 2000 Detailed Project Report Preparation & Construction Supervision of 4-lane highway project for section, Mahalape - Mach (65 km) and Molepolole - Lephephe (65.0 km), Botswana. Client : Govt. of Botswana Project Cost : Rs. 7500 M. Project Length : 2X65 Kms. Contract Condition : FIDIC Funded By : World Bank Type of Pavement : Flexible Widening to 4-lanes and strengthenin... In the state of Andhrapredesh NH5
for PWD ,Andhrapredesh in
India 2000 - 2000 Construction supervision of four laning and strengthening of Visakhapatnam-Anakapally section, including of flexible pavement about 46.2 km long Anakapally Bypass on NH-5 and 100 kms from Visakhapatnam to Srikakulam in Andhra Pradesh . Client : PWD, Andhra Pradesh Project Cost : Rs. 2300 M Project Length : 53 Kms. Contract Condition : FIDIC Funded By : ADB Type of Pavement : Flexible Construction Supervision of 2 lane roads
for in
India 2000 - 2000 Construction Supervision of 2-Lane (30 km) roads in Gurgaon, Haryana for HUDA 1988-91 (Project Cost: 30 Crores) Construction Supervision of 2-Lane road (20 km) for LPG plant at Faridabad, Haryana for BPCL, 1986-88(Project Cost:20 Crores) Construction of four-lane road (30 km), for Steel plant Authority, Visakhapatnam Andhra Pradesh, 1984-86 (Project Cost: 30 Crores). Construction Supervision of 4-lane road
for in
Iraq 2000 - 2000 Detailed Designs & Construction Supervision of 4-Lane road (22 km) Rigid Pavement, for Basra International Airport. Client : Govt. Of Iraq Project Cost : Rs. 5500 M Project Length : 22 Kms. Contract Condition : FIDIC Construction Supervision of Multi Storied Commercial Building
for Life Insurance Corporation of India in
India 2000 - 2000 Construction Supervision of Multi Storied Commercial Building at Cannaught Place. Client : LIC Project Cost : Rs. 4000 M Construction Supervision of 2-lane road
for Govt.of Mali in
Mali 2000 - 2000 Construction of 4 Lane Highway project in Mali. Client : Govt. of Mali & Holland Project Cost : Rs. 30000 M Project Length : 300 Kms. Contract Condition : FIDIC Funding By : U.N.D.P Type of Pavement : Flexible Grain Silo Project
for Fertiliser Corporation of India in
India 2000 - 2000 Grain Silo Project involving construction supervision of Fully Mechanized Grain Silo Comprising Head House, 4-batteries of Silos, conveyors at Lucknow. Client : Food Corporation of India. Project Cost : Rs 2000 M Reasearch Projects
for Council of Scientiffic Reasearch Institu in
India 2000 - 2000 Building Research |